Campus update – Jan. 14, 2020

Construction progress week of Jan. 13-17
- Continuing storm structures on site
- Rebar for footings
- Digging and pouring last footing
- Complete north CMU wall
- Continuing CMU wall on south side
- Forming on concrete walls
- Continuing pouring concrete walls
Recommended Posts

Woodmont chapel complete!
February 03, 2021

November Update – Advent is Coming!
November 03, 2020

Watch latest construction update
August 27, 2020